·OFFSHORE ·UNITED KINGDOM ·DETAILED FOUNDATION DESIGN (PRE-CONSTRUCTION) EARLY SIGNAL

Outer Dowsing: detailed monopile design awarded for 1.5 GW UK offshore wind farm

// WHAT HAPPENED

Engineering firm Wood Thilsted has been given the contract for the detailed design of up to 100 monopile foundations at the 1.5 GW Outer Dowsing offshore wind farm in the UK North Sea.

The award comes after the company finished the front-end engineering and design (FEED) work earlier this year. It was first appointed for the foundations in 2024. Now it will turn that work into detailed designs, based on site conditions, structural needs and how the foundations will be installed.

Outer Dowsing sits about 54 km off the Lincolnshire coast. TotalEnergies, Macquarie and Broadhelm Renewables, and Gulf Development are developing it. It was one of six projects chosen in the UK's Round 4 leasing in 2022, and the Crown Estate agreements were signed in January 2023. The project got development consent in February 2026.

The developers say it should power around 1.6 million homes and bring about GBP 2 billion of UK investment over its life.

This is a design contract. The source gives no dates for fabrication, installation or turbines.

// WHAT IT MEANS FOR JOBS
PHASE NOW
Detailed foundation design (pre-construction)
HIRING WINDOW
Not before 2028 · turbine installation likely later in the decade
ROUGH SCALE
Estimate: 100–200 people at peak for installation and commissioning · 12–24 months (years away)
WORKFORCE EFFECT
Crews moving across
TIMELINE · WHEN THE WORK HAPPENS
H1 26
H2 26 ▼ NOW
H1 27
H2 27
H1 28
H2 28
H1 29
H2 29
H1 30
H2 30
H1 31
H2 31
H1 32
H2 32
H1 33
H2 33
H1 34
H2 34
H1 35
H2 35
Development consent granted
confirmed
Detailed monopile design
planned
Foundation and turbine installation
planned
Operations and maintenance
long-term

Solid bar = confirmed · outlined = planned · blue = long-term jobs

ROLES NEEDED
ROLEWHENDEMANDCERTIFICATES THAT HELP
Offshore installation technician (mechanical)Estimate: 2029–2030LOWGWO BST, BTT, Sea Survival, offshore medical
Rigger / banksmanEstimate: 2029–2030LOWSlinger Signaller, GWO BST, Sea Survival
HV / commissioning technicianEstimate: 2030–2031LOWHV authorisation, GWO BST, offshore medical
Offshore service technicianEstimate: from 2031STEADYGWO BST, BTT, ART
// PLAN YOUR MOVE
Experienced technicians

Keep your offshore and HV tickets valid. Watch for turbine supplier and installation contract news, as that sets the hiring dates.

New to wind

Nothing to apply for yet. Use the time to get GWO BST and some onshore experience before UK offshore projects ramp up.

Looking for stability

Long-term service jobs on this site are the target. They are likely 5+ years away, so look at running UK wind farms for now.

Source: Offshore Wind · Scale figures are rough estimates from field experience, not official numbers.