·OFFSHORE ·UNITED KINGDOM ·PREFERRED SUPPLIER NAMED, AWAITING FINAL CONTRACT AND FID MEDIUM SIGNAL

Berwick Bank B: SSE picks Seaway7 as preferred supplier for foundations and cables

// WHAT HAPPENED

SSE Renewables has chosen Seaway7 as preferred supplier for the foundations and subsea inter-array cables at Berwick Bank B, a 1.4 GW offshore wind project in Scotland. The scope covers design, supply and installation.

This is not a final contract yet. SSE aims to take a final investment decision (FID) on the project in 2027.

SSE says the work would support 465 UK jobs, including 400 in Scotland. Seaway7 would create about 160 direct roles, led from its Aberdeen base. Another 105 jobs are expected in the UK supply chain, and 200 more through foundation marshalling at a Scottish port that has not been named yet.

Across all Berwick Bank B commitments, SSE counts around 600 jobs in the UK. This includes an operations and maintenance base at Montrose Port, with 100 long-term jobs and about 30 construction roles.

Berwick Bank B is phase two of the 4.1 GW Berwick Bank project, about 38 km off the Scottish Borders coast. The project got consent in July 2025. Phase B won a 20-year CfD in UK Allocation Round 7 in January 2026.

// WHAT IT MEANS FOR JOBS
PHASE NOW
Preferred supplier named, awaiting final contract and FID
HIRING WINDOW
Little before FID in 2027 · foundation and cable work likely from 2028 · O&M base hiring later
ROUGH SCALE
Estimate: 150–300 offshore and marshalling crew at peak · 1–2 years of foundation and cable work (source: 465 jobs overall, mostly engineering and supply chain)
WORKFORCE EFFECT
Crews moving across
TIMELINE · WHEN THE WORK HAPPENS
H2 26 ▼ NOW
H1 27
H2 27
H1 28
H2 28
H1 29
H2 29
H1 30
H2 30
H1 31
H2 31
H1 32
H2 32
H1 33
H2 33
H1 34
H2 34
H1 35
H2 35
H1 36
H2 36
H1 37
H2 37
H1 38
H2 38
H1 39
H2 39
H1 40
H2 40
H1 41
H2 41
H1 42
H2 42
H1 43
H2 43
H1 44
H2 44
H1 45
H2 45
H1 46
H2 46
H1 47
H2 47
H1 48
H2 48
H1 49
H2 49
H1 50
H2 50
H1 51
H2 51
H1 52
H2 52
H1 53
H2 53
H1 54
H2 54
H1 55
H2 55
Preferred supplier named; final contract pending
confirmed
SSE targets FID
planned
Foundation marshalling, foundation and cable installation
planned
Montrose Port O&M base: operations
long-term

Solid bar = confirmed · outlined = planned · blue = long-term jobs

ROLES NEEDED
ROLEWHENDEMANDCERTIFICATES THAT HELP
Rigger / banksman (marshalling port and vessel)Estimate: 2028–2029MEDIUMGWO BST, Slinger Signaller, Offshore medical
Cable installation / termination technicianEstimate: 2028–2029MEDIUMGWO BST, BST-Sea survival, HV cable jointing/authorisation
Mechanical technician (foundation and transition piece works)Estimate: 2028–2029MEDIUMGWO BST, BTT, Working at Height
O&M service technician (Montrose)Estimate: from about 2030STEADYGWO BST, BTT, EuP / HV authorisation
// PLAN YOUR MOVE
Experienced techs

Watch for the final contract and the 2027 FID. Seaway7 has worked on Beatrice, Seagreen and Dogger Bank, so people from those jobs are likely first in line. Keep your offshore and cable certificates up to date.

New to wind

Nothing is hiring offshore yet. Use the time to get GWO BST and sea survival. Marshalling and port roles often come before vessel jobs.

Looking for stability

The Montrose Port O&M base offers 100 long-term jobs. Those are the roles to follow if you want a settled local post in north-east Scotland.

Source: Offshore Wind (offshorewind.biz) · Scale figures are rough estimates from field experience, not official numbers.