Kumagai Gumi, a Japanese construction company, has joined Saitec Offshore Technologies and Kansai Electric Power Company (KEPCO) on the DemoSATH floating wind project in Spain. The partners have agreed to keep the prototype running at the BiMEP test site through 2027.

DemoSATH is a 2 MW turbine on a concrete twin-hull floating platform (Saitec's SATH design). It sits about 3.2 km off the Basque coast near Armintza, in roughly 85 m of water. The platform was built at the Port of Bilbao and installed in 2023. It sent its first power to the Spanish grid in September 2023. Bureau Veritas gave final prototype certification in September 2024.

In the extra period, the team will use the operating data to study how the platform behaves, improve monitoring and models, and support designs for larger floating farms. Kumagai Gumi will work on better decommissioning methods. It will also look at construction steps that could allow floating platforms to be built in large numbers. The prototype is also used for environmental research, including links with aquaculture.

// WHAT IT MEANS FOR JOBS
PHASE NOW
Operation and research (prototype extended)
HIRING WINDOW
Little hiring expected; small service needs through 2027
PLATFORM
2 MW turbine on Saitec SATH floating platform
ROUGH SCALE
Estimate: under 10 people on site · through 2027
WORKFORCE EFFECT
Crews moving across
TIMELINE · WHEN THE WORK HAPPENS
H2 23
H1 24
H2 24
H1 25
H2 25
H1 26
H2 26 ▼ NOW
H1 27
H2 27
H1 28
H2 28
H1 29
H2 29
H1 30
H2 30
DemoSATH installed and first power
confirmed
Extended prototype operation at BiMEP
confirmed
Possible larger floating projects using the results
long-term

Solid bar = confirmed · outlined = planned · blue = long-term jobs

ROLES NEEDED
ROLEWHENDEMANDCERTIFICATES THAT HELP
Offshore service technician (floating)2026–2027, as neededLOWGWO BST, BTT, Sea Survival
Electrical / monitoring technician2026–2027, as neededLOWGWO BST, LV/HV authorisation
// PLAN YOUR MOVE
Experienced techs

Floating experience is rare. Keep an eye on this and similar demo sites, as the lessons feed into larger floating farms later.

New to wind

Do not plan around this project. It is one small turbine. Get GWO BST and BTT first, then aim at larger offshore projects.

Looking for stability

A test turbine running to 2027 is not a long-term employer. Look to bigger floating or fixed offshore operators for steady work.

Source: Offshore Wind · Scale figures are rough estimates from field experience, not official numbers.