Birkhill Wood: Balfour Beatty to build the grid substation for three Dogger Bank wind farms

// WHAT HAPPENED

Balfour Beatty has won a contract from National Grid for the first phase of the Birkhill Wood 400 kV substation in East Yorkshire. The substation will link three planned offshore wind farms to the UK grid: Dogger Bank South East, Dogger Bank South West and Dogger Bank D.

The contract covers early design work and enabling works to prepare the site. Enabling works have already started. Main construction is expected to begin in 2027. National Grid got planning consent for the site in June 2026.

Dogger Bank South East and South West are 1.5 GW each, developed by RWE and Masdar. Both have development consent (May 2026) and CfDs from Allocation Round 7. Commissioning is expected in 2031 and 2032, with a final investment decision targeted for 2027.

Dogger Bank D, from SSE Renewables and Equinor, is up to 1.5 GW. It has a seabed lease but still needs development consent and an investment decision.

Balfour Beatty says the whole substation project will employ about 200 people at peak.

// WHAT IT MEANS FOR JOBS
PHASE NOW
Substation enabling works and detailed design
HIRING WINDOW
Civil and substation work 2027–2029 · turbine work likely from about 2029–2032 (estimate)
ROUGH SCALE
Substation: about 200 people at peak (stated). Turbine work not yet defined; likely hundreds of people over several years (rough estimate)
WORKFORCE EFFECT
Mixed: new demand + crews moving across
TIMELINE · WHEN THE WORK HAPPENS
H2 26 ▼ NOW
H1 27
H2 27
H1 28
H2 28
H1 29
H2 29
H1 30
H2 30
H1 31
H2 31
H1 32
H2 32
Birkhill Wood enabling works and design
confirmed
Birkhill Wood main construction (start 2027)
planned
Dogger Bank South East/South West FID target
planned
Dogger Bank South East commissioning (2031) and South West (2032)
planned
Dogger Bank D: consent and FID still needed
long-term

Solid bar = confirmed · outlined = planned · blue = long-term jobs

ROLES NEEDED
ROLEWHENDEMANDCERTIFICATES THAT HELP
HV / substation commissioning technician2028–2030 (estimate)MEDIUMHV authorisation / senior authorised person, GWO BST
Electrical installation technician (LV)2027–2029 (estimate)MEDIUMElectrical qualifications, GWO BST, site safety card
Offshore turbine installation technicianFrom about 2030 (estimate)LOWGWO BST, BTT, Sea Survival, OPITO
// PLAN YOUR MOVE
Experienced technicians

Keep HV authorisations current. Substation commissioning work should come before turbine work, and it is worth watching for contractor announcements.

New to wind

Build your base now with GWO BST and basic electrical skills. Turbine work on these projects is still years away, so no rush.

Looking for stability

Dogger Bank has several phases, so long-term service work is likely after 2032. Dogger Bank D is not yet approved, so do not count on it.

Source: Offshore Wind (offshorewind.biz) · Scale figures are rough estimates from field experience, not official numbers.