·OFFSHORE ·NORWAY ·SUPPORT AWARDED – PROJECT DEVELOPMENT MEDIUM SIGNAL

Norway picks two floating wind projects for METCentre, about 74 MW in total

// WHAT HAPPENED

Norway's state agency Enova has picked two winners in its competition for small-scale commercial floating wind. Both projects are planned at METCentre outside Karmøy. Each is about 37 MW, so the total is around 74 MW.

Five companies applied for NOK 9 billion in total. Each project can get up to NOK 2 billion in support. The decision came at the end of October, after an earlier expectation of May. Projects had to use roughly one to five turbines and aim to start up within five years.

METCentre holds a licence for up to six floating turbines (82.7 MW), plus the existing 2.3 MW Zephyros turbine. It also has reserved grid capacity and a plan for a new 66 kV export cable.

The source names the winners in two different ways. One version says Fortius Offshore Wind and Fram Wind Solutions. Another says Deep Wind Offshore and Fram Wind Solutions. No contractors, turbine models or construction dates are given. Suppliers will hear more as buying needs become clear.

// WHAT IT MEANS FOR JOBS
PHASE NOW
Support awarded – project development
HIRING WINDOW
Little before 2028 · installation crews roughly 2029–2031 · service from about 2030
ROUGH SCALE
Estimate: 20–50 technicians at peak · a few months of offshore installation per project
WORKFORCE EFFECT
Crews moving across
TIMELINE · WHEN THE WORK HAPPENS
H2 26 ▼ NOW
H1 27
H2 27
H1 28
H2 28
H1 29
H2 29
H1 30
H2 30
H1 31
H2 31
H1 32
H2 32
H1 33
H2 33
H1 34
H2 34
H1 35
H2 35
Enova selects two winners
confirmed
Engineering, permits, supplier selection
planned
Fabrication and assembly
planned
Tow-out, installation, commissioning
planned
Operation and maintenance
long-term

Solid bar = confirmed · outlined = planned · blue = long-term jobs

ROLES NEEDED
ROLEWHENDEMANDCERTIFICATES THAT HELP
Floating turbine assembly / installation technician2028–2030LOWGWO BST, BTT, Sea Survival
HV / commissioning technician (66 kV)2029–2031LOWHV authorisation, GWO BST
Rigger / slinger signaller2028–2030LOWSlinger Signaller, GWO BST, ART
Offshore service technicianFrom about 2031STEADYGWO BST, BTT, Sea Survival
// PLAN YOUR MOVE
Experienced techs

Floating work is niche in Norway. Keep your offshore and HV papers current and watch for supplier calls through Norwegian Offshore Wind and METCentre.

New to wind

Do not wait for this. The projects are small and years away. Get GWO BST and BTT now and look at wider offshore jobs first.

Looking for stability

The long-term O&M work could be steady, but only two small projects. Treat it as a bonus, not your main plan.

Source: Norwegian Offshore Wind · Scale figures are rough estimates from field experience, not official numbers.