CVOW: 44 of 176 turbines installed at the largest US offshore wind farm

// WHAT HAPPENED

Dominion Energy gave an update on Coastal Virginia Offshore Wind (CVOW) with its Q3 2026 results on 30 October. 44 of the 176 Siemens Gamesa 14 MW turbines are installed, and the 45th is being installed now.

The first turbine went up in January 2026. First power reached the grid in March 2026. Each turbine becomes operational as it is finished.

The vessel Charybdis is doing the installation. It is the first Jones Act-compliant wind turbine installation vessel. Dominion ordered it, and Seatrium built it at the AmFELS yard in Brownsville, Texas.

The base rate is two days per turbine, not counting load-out, transit, weather and maintenance. Dominion says this rate has not changed so far. The company still expects the 176th turbine by the end of 2027. Earlier it had aimed to finish in early 2027, and it added contingency time for weather, vessel maintenance, load-out and long jacking operations.

Two offshore substations are already commissioned. The third is expected to be energised by the end of 2026.

The project is 2.6 GW. Dominion also says the cost of energy fell from USD 83/MWh to USD 62/MWh, because REC revenues are higher.

// WHAT IT MEANS FOR JOBS
PHASE NOW
Turbine installation (44 of 176 done) and substation commissioning
HIRING WINDOW
Now – end 2027 · O&M from 2027
PLATFORM
Siemens Gamesa 14 MW
ROUGH SCALE
Estimate: 150–300 people on installation, commissioning and logistics · about 14 more months of installation
WORKFORCE EFFECT
Crews moving across
TIMELINE · WHEN THE WORK HAPPENS
H1 26
H2 26 ▼ NOW
H1 27
H2 27
H1 28
H2 28
H1 29
H2 29
H1 30
H2 30
Turbine installation (first turbine Jan 2026)
confirmed
First power to grid
confirmed
Third offshore substation energised
confirmed
Final (176th) turbine expected
planned
Operations and maintenance
long-term

Solid bar = confirmed · outlined = planned · blue = long-term jobs

ROLES NEEDED
ROLEWHENDEMANDCERTIFICATES THAT HELP
Offshore turbine installation technician (mechanical)Now – end 2027STEADYGWO BST, BTT, Sea Survival; US offshore medical
Rigger / banksman / crane crewNow – end 2027STEADYGWO Basic Safety Training, Slinger Signaller, Rigging
Electrical / commissioning technician2026-H2 – 2028MEDIUMGWO BST, BTT, electrical authorisation, HV safety training
Service technician (O&M)From 2027MEDIUMGWO BST, BTT, Sea Survival, Siemens Gamesa training
// PLAN YOUR MOVE
Experienced technicians

Installation runs at a steady pace to the end of 2027. Contact the installation contractors now and ask about O&M roles for when it ends.

New to wind

Get GWO BST and Sea Survival first. US offshore jobs usually want offshore experience, so look at onshore or port roles to start.

Looking for stability

Aim at the long-term O&M team. Turbines are handed over one by one, so service jobs start before the installation finishes.

Source: Offshore Wind (offshorewind.biz) · Scale figures are rough estimates from field experience, not official numbers.