Ecowende: all 52 turbines installed at Dutch offshore wind farm, final commissioning ahead

// WHAT HAPPENED

Ecowende has finished installing all 52 turbines at its Hollandse Kust West offshore wind farm in the Dutch North Sea. It announced this on 2 November 2026. The campaign ran for exactly five months, starting on 30 May 2026, with Van Oord and Vestas.

The farm uses Vestas V236-15.0 MW turbines and will deliver about 760 MW. It lies roughly 53 km off IJmuiden. Ecowende is a joint venture of Shell, Eneco and Chubu Electric Power.

Vestas made the components and handled transport and pre-assembly at Eemshaven. Van Oord shipped them out on the vessel Boreas, which has a 3,310-tonne main crane. Vestas did the installation and commissioning with that crane.

The foundations (52 monopiles) were finished earlier in 2026. First power came in July, through the TenneT grid connection. Installation does not mean commissioning is done. The project still targets full operation by the end of 2026.

// WHAT IT MEANS FOR JOBS
PHASE NOW
Final commissioning (turbine installation complete)
HIRING WINDOW
Now – end 2026 (commissioning) · service roles from 2027
PLATFORM
Vestas V236-15.0 MW
ROUGH SCALE
Estimate: 30–60 people for the remaining commissioning · 1–2 months, then a small service team for operations
WORKFORCE EFFECT
Crews moving across
TIMELINE · WHEN THE WORK HAPPENS
H2 25
H1 26
H2 26 ▼ NOW
H1 27
H2 27
H1 28
H2 28
H1 29
H2 29
H1 30
H2 30
Monopile foundations installed
confirmed
Turbine installation (30 May – 30 Oct)
confirmed
First power (July) and final commissioning
confirmed
Operations and maintenance
long-term

Solid bar = confirmed · outlined = planned · blue = long-term jobs

ROLES NEEDED
ROLEWHENDEMANDCERTIFICATES THAT HELP
Commissioning technician (electrical)Now – Dec 2026MEDIUMGWO BST, BTT, GWO Sea Survival, LV/HV authorisation
Mechanical completion technicianNow – Dec 2026LOWGWO BST, BTT, GWO Sea Survival
Service technician (offshore)From 2027STEADYGWO BST, BTT, Sea Survival, Vestas OEM training
// PLAN YOUR MOVE
Experienced technicians

The installation crews will be freed up now. Ask Vestas and other offshore contractors about the next campaigns. Commissioning experience on V236 turbines is a plus.

New to wind

Very little new hiring is likely here, as the construction work is almost done. Get your GWO BST and Sea Survival certificates so you are ready when the next project starts.

Looking for stability

Watch for long-term service jobs on this farm from 2027. Operation and maintenance work lasts for years.

Source: HMT News · Scale figures are rough estimates from field experience, not official numbers.