← ALL WIND NEWS

·OFFSHORE ·GERMANY ·CONTRACT AWARDED, OPERATIONS AND MAINTENANCE HANDOVER STRONG SIGNAL

alpha ventus: Deutsche Windtechnik wins service contract as Germany's first offshore wind farm keeps running

// WHAT HAPPENED

Deutsche Windtechnik has won the service and maintenance contract for all 12 turbines at the alpha ventus offshore wind farm (60 MW) in the German North Sea. Work starts in January 2027.

The client is Ocean Breeze Energy, which is taking over the site from EWE, RWE and Vattenfall. The farm has six Senvion 5M and six AREVA Multibrid M5000 turbines. It lies about 45 km north of Borkum and was commissioned in 2010.

At first, Deutsche Windtechnik will do maintenance, troubleshooting and technical support. From September 2027, the scope grows to remote monitoring, offshore control centre services, grid management and 24/7 alarm handling.

The company looked after these turbines before: the Senvion units from 2017 and the Multibrid units from early 2020, until the contracts ended in December 2024.

Ocean Breeze Energy said in October 2026 that it will keep the farm running beyond its planned 20-year life. This reverses the 2025 plan to decommission it. The owner also runs the 400 MW BARD Offshore 1 farm nearby. Deutsche Windtechnik runs its offshore service work from Borkum, where it also covers Riffgat and Trianel Windpark Borkum I.

// WHAT IT MEANS FOR JOBS
PHASE NOW
Contract awarded, operations and maintenance handover
HIRING WINDOW
Late 2026 – Q1 2027 · control centre roles from Sep 2027
PLATFORM
Senvion 5M and AREVA Multibrid M5000
ROUGH SCALE
Estimate: 8–15 people (service techs plus control room staff) · multi-year
WORKFORCE EFFECT
Crews moving across
TIMELINE · WHEN THE WORK HAPPENS
H2 26 ▼ NOW
H1 27
H2 27
H1 28
H2 28
H1 29
H2 29
H1 30
H2 30
Deutsche Windtechnik starts turbine service
confirmed
Remote monitoring, control centre, 24/7 alarm handling added
confirmed
Operation beyond original 20-year life
long-term

Solid bar = confirmed · outlined = planned · blue = long-term jobs

ROLES NEEDED
ROLEWHENDEMANDCERTIFICATES THAT HELP
Offshore service technicianDec 2026 – Q1 2027MEDIUMGWO BST, BTT, Sea Survival; offshore medical
Electrical / HV service technician2027STEADYGWO BST, EuP / HV authorisation
Control centre / alarm operatorFrom Sep 2027LOWSCADA knowledge, wind technician background
// PLAN YOUR MOVE
Experienced techs

Senvion 5M and Multibrid M5000 experience is rare and useful. Contact Deutsche Windtechnik's Borkum base, as the same team has serviced these turbines before.

New to wind

This is a small site, so few entry jobs. Get GWO BST and BTT first and watch Deutsche Windtechnik's Borkum offshore openings across its other farms.

Looking for stability

The decision to extend the farm's life gives multi-year work. Control centre roles from September 2027 may suit techs who want fewer offshore rotations.

Source: Offshore Wind · Scale figures are rough estimates from field experience, not official numbers.