Revolution Wind fully commissioned in the US; Sunrise Wind turbine commissioning next

// WHAT HAPPENED

Revolution Wind (704 MW), built by Ørsted and Skyborn Renewables, reached full commissioning in October 2026. It now supplies power to Rhode Island (400 MW) and Connecticut (304 MW). The farm has 65 Siemens Gamesa SG 11.0-200 DD turbines. The first one went up in September 2024, and the last ones were installed in September 2026. Power first reached the New England grid in March 2026.

The project still faces a legal challenge. In October, the US Department of Justice and the Department of the Interior asked a federal court to send the approval of its construction and operations plan back to the government for review.

Ørsted's Q3 report, published on 5 November, also covers Sunrise Wind (924 MW) off New York. All turbine foundations are installed. Turbine and inter-array cable installation is underway, as is commissioning of the offshore converter station. Turbine commissioning should start around the end of 2026. Full commissioning is still planned for the second half of 2027. The farm will have 84 Siemens Gamesa 11 MW turbines.

// WHAT IT MEANS FOR JOBS
PHASE NOW
Revolution Wind: handover to operations. Sunrise Wind: turbine and cable installation
HIRING WINDOW
Now – 2H 2027 (Sunrise Wind) · service roles from 2027
PLATFORM
Siemens Gamesa SG 11.0-200 DD (Revolution Wind); Siemens Gamesa 11 MW (Sunrise Wind)
ROUGH SCALE
Estimate: about 100–200 people on Sunrise Wind offshore and port work over roughly 12 months; a smaller service team for Revolution Wind
WORKFORCE EFFECT
Crews moving across
TIMELINE · WHEN THE WORK HAPPENS
H2 24
H1 25
H2 25
H1 26
H2 26 ▼ NOW
H1 27
H2 27
H1 28
H2 28
H1 29
H2 29
H1 30
H2 30
H1 31
H2 31
H1 32
H2 32
H1 33
H2 33
H1 34
H2 34
H1 35
H2 35
H1 36
H2 36
Revolution Wind turbine installation
confirmed
Revolution Wind full commissioning
confirmed
Sunrise Wind turbine and cable installation
confirmed
Sunrise Wind turbine commissioning and full commissioning
planned
Operations and maintenance, both farms
long-term

Solid bar = confirmed · outlined = planned · blue = long-term jobs

ROLES NEEDED
ROLEWHENDEMANDCERTIFICATES THAT HELP
Turbine installation technician (mechanical/electrical)Now – mid 2027STEADYGWO BST, BTT, GWO Sea Survival, offshore medical
Commissioning technician (turbine and HV)Late 2026 – 2H 2027MEDIUMGWO BST, HV authorisation, manufacturer training
Rigger / banksmanNow – mid 2027LOWGWO Slinger Signaller, Basic Safety Training, Sea Survival
Offshore service technicianFrom 2027STEADYGWO BST, BTT, ART, Sea Survival
// PLAN YOUR MOVE
Experienced techs

Revolution Wind crews are likely to move to Sunrise Wind, so contact contractors on Sunrise Wind commissioning early. Keep your HV and offshore certificates valid.

New to wind

Little net new hiring is likely, because crews are moving across. Get GWO BST and BTT first, and look at service or port roles in the US Northeast.

Looking for stability

Both farms will need service teams for years. Watch for long-term operations roles from 2027. Note the legal risk around Revolution Wind's approval.

Source: Offshore Wind (offshorewind.biz) · Scale figures are rough estimates from field experience, not official numbers.