Vattenfall signs final deals for Hesselø and Holmsland offshore wind farms in Denmark

// WHAT HAPPENED

Vattenfall and the Danish Energy Agency have signed the final agreements for two new offshore wind projects, Hesselø and Holmsland. Together they add at least 1.8 GW to Denmark's offshore pipeline.

Hesselø will have a minimum capacity of 800 MW and sits in the Kattegat. Holmsland was called North Sea I Mid before. It will have at least 1 GW in the North Sea, near Hvide Sande. The new name reflects its spot off the Danish west coast.

Vattenfall won both sites in the August 2026 tender with the lowest bids. Denmark launched this tender in November 2025, after an earlier round got no bids. The new rules include two-sided contracts for difference, a form of state support.

Vattenfall aims to commission the wind farms in 2032. Construction still depends on final investment decisions and the needed approvals. The company runs five offshore wind farms in Denmark today. It is also developing Nordlicht in Germany and Zeevonk in the Netherlands.

// WHAT IT MEANS FOR JOBS
PHASE NOW
Development and permitting (before final investment decision)
HIRING WINDOW
Little direct hiring until ~2029 · installation likely 2030–2032 · O&M from 2032
ROUGH SCALE
Estimate: 150–250 people at peak across both sites · about 2 years of installation work
WORKFORCE EFFECT
Mixed: new demand + crews moving across
TIMELINE · WHEN THE WORK HAPPENS
H2 26 ▼ NOW
H1 27
H2 27
H1 28
H2 28
H1 29
H2 29
H1 30
H2 30
H1 31
H2 31
H1 32
H2 32
H1 33
H2 33
H1 34
H2 34
H1 35
H2 35
H1 36
H2 36
H1 37
H2 37
H1 38
H2 38
H1 39
H2 39
H1 40
H2 40
H1 41
H2 41
H1 42
H2 42
H1 43
H2 43
H1 44
H2 44
H1 45
H2 45
H1 46
H2 46
H1 47
H2 47
H1 48
H2 48
H1 49
H2 49
H1 50
H2 50
H1 51
H2 51
H1 52
H2 52
H1 53
H2 53
H1 54
H2 54
H1 55
H2 55
H1 56
H2 56
H1 57
H2 57
H1 58
H2 58
Tender won and final agreements signed
confirmed
Development, permits and final investment decisions
planned
Construction and turbine installation (estimate)
planned
Target commissioning
confirmed
Operations and maintenance
long-term

Solid bar = confirmed · outlined = planned · blue = long-term jobs

ROLES NEEDED
ROLEWHENDEMANDCERTIFICATES THAT HELP
Installation technician (mechanical/electrical)2030–2032MEDIUMGWO BST, BTT, GWO BTT offshore modules, Sea Survival
Rigger / banksman2030–2032MEDIUMGWO BST, Slinger Signaller, Rigger
HV / commissioning technician2031–2032MEDIUMHV authorisation, EuP, GWO BST
Service technicianFrom 2032STEADYGWO BST, BTT, Sea Survival, OEM training
// PLAN YOUR MOVE
Experienced technicians

Nothing to apply for yet. Watch for turbine supplier and installation contract news in 2027–2029, as these will set the crew needs.

New to wind

You have time. Get GWO BST and BTT now, and offshore basics such as Sea Survival, so you are ready when offshore projects in the region ramp up.

Looking for stability

Long-term O&M work in Denmark is the steady prize here, from 2032. Vattenfall already runs five Danish offshore wind farms, which may be an early route in.

Source: Offshore Wind · Scale figures are rough estimates from field experience, not official numbers.