·OFFSHORE ·NETHERLANDS, UNITED KINGDOM ·FOUNDATION MANUFACTURING SLOWDOWN (PRE-FID) EARLY SIGNAL

Sif closes one monopile line and seeks bridge funding while a 2 GW project waits for a go-ahead

// WHAT HAPPENED

Dutch foundation maker Sif said on 6 November 2026 that it has a cash problem and sees material uncertainty about continuing as a going concern over the next twelve months.

To save cash, Sif will close one of three production lines at Maasvlakte 2 from Q4 2026. It will also scale back work at Roermond from Q1 2027.

The reason is a ~2 GW offshore project that is still waiting for the client's final investment decision. Sif holds 190 kton of capacity for it. Monopile production is planned for summer 2027 (earlier guidance: May–August 2027). The company is in talks with lenders, the Dutch State, its largest shareholder and others. No binding bridge deal exists yet, and its EUR 50 million credit facility is unavailable for now.

Sif says it will still finish existing orders, including East Anglia Two. Cash stood at EUR 35.1 million at the end of September. An extraordinary shareholder meeting is set for 22 December. Sif expects foundation demand to return from 2029.

// WHAT IT MEANS FOR JOBS
PHASE NOW
Foundation manufacturing slowdown (pre-FID)
HIRING WINDOW
Weak through 2027 · possible recovery if the 2 GW project gets FID, more broadly from 2029
ROUGH SCALE
Estimate: no new hiring; production roles at risk at two factories for 2027. Effect on installation crews is small and delayed.
WORKFORCE EFFECT
Crews moving across
TIMELINE · WHEN THE WORK HAPPENS
H2 26 ▼ NOW
H1 27
H2 27
H1 28
H2 28
H1 29
H2 29
Maasvlakte 2: one of three lines closed
confirmed
Roermond: reduced operations
confirmed
Shareholder meeting on equity authorisation (22 Dec)
confirmed
Planned start of monopile production for 2 GW project (needs FID)
planned
Expected return of foundation demand
long-term

Solid bar = confirmed · outlined = planned · blue = long-term jobs

ROLES NEEDED
ROLEWHENDEMANDCERTIFICATES THAT HELP
Steel fabrication / welding-related technicianNow – 2027 (cuts likely)LOWGWO BST, trade welding certificates
Rigger / crane banksman (yard and load-out)2027, depends on FIDLOWSlinger Signaller, GWO BST
Offshore installation technician2028 onwards, if projects proceedLOWGWO BST, BTT, Offshore sea survival
// PLAN YOUR MOVE
Experienced technicians

Do not count on foundation or yard work in 2027. Keep an eye on the FID news, and look at installation and service work on projects that are already under construction.

New to wind

Do not plan around Dutch monopile factory jobs for now. Get GWO BST and basic certificates and aim for service or onshore roles, where hiring is steadier.

Looking for stability

Favour operations and maintenance employers over manufacturing. Sif itself says the funding is uncertain, so treat any offer from its supply chain carefully.

Source: Offshore Wind (offshorewind.biz) · Scale figures are rough estimates from field experience, not official numbers.