Berwick Bank B: Siemens Energy picked as preferred turbine supplier, installation planned 2030–2032
SSE has chosen Siemens Energy as preferred supplier for the wind turbines and offshore substation platforms at Berwick Bank B, a 1.4 GW offshore wind project in the outer Firth of Forth, about 38 km off the Scottish coast. Siemens Energy will deliver the substations together with Smulders-HSM.
This is not a final contract. It depends on SSE's final investment decision, expected in late 2027, and on a final contract award.
SSE says the selection supports 2,677 UK jobs across manufacturing, engineering, project delivery and servicing. Of these, 2,222 are tied to Siemens Energy operations in northern England and 455 are in Scotland. Berwick Bank B commitments now total 3,272 UK jobs.
Earlier commitments include Seaway7 as preferred supplier for foundations and inter-array cables, and a Montrose Port base with about 100 long-term O&M jobs and around 30 construction roles.
The project won a CfD in UK Allocation Round 7. If the FID goes ahead, preparatory offshore works could start in 2028. Turbine and substation installation would run from 2030 to 2032.
Solid bar = confirmed · outlined = planned · blue = long-term jobs
| ROLE | WHEN | DEMAND | CERTIFICATES THAT HELP |
|---|---|---|---|
| Offshore installation technician (mechanical/electrical) | 2030–2032 | MEDIUM | GWO BST, BTT, Sea Survival, offshore medical |
| Rigger / banksman | 2030–2032 | MEDIUM | GWO Slinger Signaller, Advanced Rigging, GWO BST |
| HV / commissioning technician | 2031–2032 | MEDIUM | HV authorisation, GWO BST, offshore medical |
| Service technician (O&M, Montrose) | From 2032 | STEADY | GWO BST, BTT, ART, HV authorisation |
Nothing to apply for yet. Keep your offshore and HV certificates valid. Installation is the 2030–2032 window, so watch for contractor announcements after the 2027 FID.
You have time. Get GWO BST and BTT now and build experience on other UK projects. Entry-level installation roles will be easier to reach in 2029–2030.
The long-term O&M jobs at Montrose are the stable option, starting after construction ends. Services roles in Scotland should be worth following.
Source: Offshore Wind · Scale figures are rough estimates from field experience, not official numbers.