·OFFSHORE ·UNITED KINGDOM ·FINANCIAL CLOSE DONE; FABRICATION OF FOUNDATIONS UNDER WAY, OFFSHORE CONSTRUCTION STARTS EARLY 2027 STRONG SIGNAL

Vanguard West and East: RWE and KKR close GBP 11.1 billion financing for 2.8 GW UK offshore wind

// WHAT HAPPENED

RWE and KKR have completed their 50:50 joint venture for Vanguard West and Vanguard East, two UK offshore wind farms off the coast of Norfolk. They also closed a financing package of GBP 11.1 billion in cash facilities plus GBP 1.7 billion in ancillary facilities, provided by 35 banks. Total investment, including transmission, is about GBP 12 billion.

Each wind farm will have about 1.4 GW of capacity, sited 50–80 km offshore. Both won 20-year CfDs in the UK's seventh allocation round at GBP 91.20 per MWh (2024 prices). RWE leads delivery for the partnership.

RWE has placed firm orders with Vestas for 92 V236-15 MW turbines per project. Haizea Wind Group has started making monopiles for Vanguard West. Lamprell will build 184 transition pieces for the two sites.

Offshore construction is set to start in early 2027. The first foundation at Vanguard West is planned for H1 2027, with Vanguard East after it. Full commissioning is expected in 2030.

// WHAT IT MEANS FOR JOBS
PHASE NOW
Financial close done; fabrication of foundations under way, offshore construction starts early 2027
HIRING WINDOW
Late 2026 – 2027 (foundations, marine) · 2028 – 2030 (turbine installation, commissioning) · O&M after 2030
PLATFORM
Vestas V236-15 MW
ROUGH SCALE
Estimate: 150–300 people at peak across installation, commissioning and logistics · about 3–4 years of offshore work
WORKFORCE EFFECT
Mixed: new demand + crews moving across
TIMELINE · WHEN THE WORK HAPPENS
H2 26 ▼ NOW
H1 27
H2 27
H1 28
H2 28
H1 29
H2 29
H1 30
H2 30
H1 31
H2 31
H1 32
H2 32
H1 33
H2 33
H1 34
H2 34
H1 35
H2 35
H1 36
H2 36
H1 37
H2 37
H1 38
H2 38
H1 39
H2 39
H1 40
H2 40
H1 41
H2 41
H1 42
H2 42
H1 43
H2 43
H1 44
H2 44
H1 45
H2 45
H1 46
H2 46
H1 47
H2 47
H1 48
H2 48
H1 49
H2 49
H1 50
H2 50
H1 51
H2 51
H1 52
H2 52
H1 53
H2 53
H1 54
H2 54
H1 55
H2 55
Financial close and JV completed
confirmed
Monopile and transition piece manufacturing
confirmed
Offshore construction start; first foundation at Vanguard West
confirmed
Vanguard East foundations and turbine installation (estimated window)
planned
Full commissioning
confirmed
Operations and maintenance
long-term

Solid bar = confirmed · outlined = planned · blue = long-term jobs

ROLES NEEDED
ROLEWHENDEMANDCERTIFICATES THAT HELP
Rigger / banksman (foundation and turbine lifting)2027 – 2029MEDIUMGWO BST, Slinger Signaller, GWO Basic Technical Training, offshore medical
Mechanical installation technician2028 – 2030MEDIUMGWO BST, BTT, GWO Sea Survival, OPITO
Electrical / commissioning technician2028 – 2030MEDIUMGWO BST, BTT, LV authorisation, EuP
HV technician2028 – 2030MEDIUMHV authorisation, GWO BST, offshore medical
Service technician (O&M)2030 onwardsSTEADYGWO BST, BTT, ART, sea survival
// PLAN YOUR MOVE
Experienced technicians

Turbine work comes after foundations. Watch for Vestas and its installation contractors announcing crew needs from 2027, and plan for roles from 2028.

New to wind

Get your GWO BST and sea survival done and in date before 2028. Entry roles such as assistant or logistics positions are likely to appear nearer turbine installation.

Looking for stability

The 2030 finish leads into about 25 years of operations. A service technician route with the future operator and the turbine service team offers the longest-lasting work.

Source: Offshore Wind · Scale figures are rough estimates from field experience, not official numbers.