Vanguard West and East: RWE and KKR close GBP 11.1 billion financing for 2.8 GW UK offshore wind
RWE and KKR have completed their 50:50 joint venture for Vanguard West and Vanguard East, two UK offshore wind farms off the coast of Norfolk. They also closed a financing package of GBP 11.1 billion in cash facilities plus GBP 1.7 billion in ancillary facilities, provided by 35 banks. Total investment, including transmission, is about GBP 12 billion.
Each wind farm will have about 1.4 GW of capacity, sited 50–80 km offshore. Both won 20-year CfDs in the UK's seventh allocation round at GBP 91.20 per MWh (2024 prices). RWE leads delivery for the partnership.
RWE has placed firm orders with Vestas for 92 V236-15 MW turbines per project. Haizea Wind Group has started making monopiles for Vanguard West. Lamprell will build 184 transition pieces for the two sites.
Offshore construction is set to start in early 2027. The first foundation at Vanguard West is planned for H1 2027, with Vanguard East after it. Full commissioning is expected in 2030.
Solid bar = confirmed · outlined = planned · blue = long-term jobs
| ROLE | WHEN | DEMAND | CERTIFICATES THAT HELP |
|---|---|---|---|
| Rigger / banksman (foundation and turbine lifting) | 2027 – 2029 | MEDIUM | GWO BST, Slinger Signaller, GWO Basic Technical Training, offshore medical |
| Mechanical installation technician | 2028 – 2030 | MEDIUM | GWO BST, BTT, GWO Sea Survival, OPITO |
| Electrical / commissioning technician | 2028 – 2030 | MEDIUM | GWO BST, BTT, LV authorisation, EuP |
| HV technician | 2028 – 2030 | MEDIUM | HV authorisation, GWO BST, offshore medical |
| Service technician (O&M) | 2030 onwards | STEADY | GWO BST, BTT, ART, sea survival |
Turbine work comes after foundations. Watch for Vestas and its installation contractors announcing crew needs from 2027, and plan for roles from 2028.
Get your GWO BST and sea survival done and in date before 2028. Entry roles such as assistant or logistics positions are likely to appear nearer turbine installation.
The 2030 finish leads into about 25 years of operations. A service technician route with the future operator and the turbine service team offers the longest-lasting work.
Source: Offshore Wind · Scale figures are rough estimates from field experience, not official numbers.