Cadeler signs exclusivity deal for foundation and turbine installation at a large UK offshore wind farm from about 2030
Cadeler said on 11 November that it signed an exclusivity agreement to install foundations and wind turbines at a large offshore wind farm in the UK. The client and the project are not named.
Work is expected to start around 2030. For the foundation campaign, Cadeler plans to use two vessels: one A-Class and one O-Class. The turbines would be installed by a P-Class vessel.
The news came soon after Cadeler won a contract to transport and install turbines at the 1.2 GW Dogger Bank C wind farm in the UK. That job will use the newbuild A-class vessel Wind Apex, which is still being built at the COSCO Shipping Heavy Industry yard in China.
Earlier this year Cadeler also signed firm contracts with COSCO Shipping Offshore for two new T-class foundation installation vessels. They are due for delivery in 2030 and 2031.
An exclusivity agreement is not yet a final contract, so details may change.
Solid bar = confirmed · outlined = planned · blue = long-term jobs
| ROLE | WHEN | DEMAND | CERTIFICATES THAT HELP |
|---|---|---|---|
| Offshore installation technician (mechanical) | 2030 onward | MEDIUM | GWO BST, BTT, Sea Survival, offshore medical |
| Rigger / banksman / slinger signaller | 2030 onward | MEDIUM | GWO BST, Slinger Signaller, Rigging, Sea Survival |
| HV / commissioning technician | Around 2031 onward | STEADY | HV authorisation, GWO BST, Sea Survival |
This is far off and not yet a final contract. Keep offshore installation and rigging experience current, and watch for the project name and contract signing.
Use the time to get GWO BST and BTT and basic offshore training. Dogger Bank C and other nearer projects are better places to start.
Large UK projects bring long O&M years after installation. Plan for service roles from the early 2030s rather than short installation jobs.
Source: Offshore Wind · Scale figures are rough estimates from field experience, not official numbers.