// WHAT HAPPENED

Cadeler said on 11 November that it signed an exclusivity agreement to install foundations and wind turbines at a large offshore wind farm in the UK. The client and the project are not named.

Work is expected to start around 2030. For the foundation campaign, Cadeler plans to use two vessels: one A-Class and one O-Class. The turbines would be installed by a P-Class vessel.

The news came soon after Cadeler won a contract to transport and install turbines at the 1.2 GW Dogger Bank C wind farm in the UK. That job will use the newbuild A-class vessel Wind Apex, which is still being built at the COSCO Shipping Heavy Industry yard in China.

Earlier this year Cadeler also signed firm contracts with COSCO Shipping Offshore for two new T-class foundation installation vessels. They are due for delivery in 2030 and 2031.

An exclusivity agreement is not yet a final contract, so details may change.

// WHAT IT MEANS FOR JOBS
PHASE NOW
Pre-contract (exclusivity agreement)
HIRING WINDOW
Not before 2029 – 2030 · installation work from about 2030
ROUGH SCALE
Estimate: 150–250 people across foundation and turbine vessels and port teams · multi-year campaign from about 2030
WORKFORCE EFFECT
Mixed: new demand + crews moving across
TIMELINE · WHEN THE WORK HAPPENS
H2 26 ▼ NOW
H1 27
H2 27
H1 28
H2 28
H1 29
H2 29
H1 30
H2 30
H1 31
H2 31
H1 32
H2 32
H1 33
H2 33
H1 34
H2 34
H1 35
H2 35
H1 36
H2 36
H1 37
H2 37
H1 38
H2 38
H1 39
H2 39
H1 40
H2 40
H1 41
H2 41
H1 42
H2 42
H1 43
H2 43
H1 44
H2 44
H1 45
H2 45
H1 46
H2 46
H1 47
H2 47
H1 48
H2 48
H1 49
H2 49
H1 50
H2 50
H1 51
H2 51
H1 52
H2 52
H1 53
H2 53
H1 54
H2 54
H1 55
H2 55
Dogger Bank C turbine installation (Wind Apex)
planned
Cadeler T-class foundation vessels delivered
confirmed
Unnamed UK project: foundation and turbine installation
planned
Operations and maintenance
long-term

Solid bar = confirmed · outlined = planned · blue = long-term jobs

ROLES NEEDED
ROLEWHENDEMANDCERTIFICATES THAT HELP
Offshore installation technician (mechanical)2030 onwardMEDIUMGWO BST, BTT, Sea Survival, offshore medical
Rigger / banksman / slinger signaller2030 onwardMEDIUMGWO BST, Slinger Signaller, Rigging, Sea Survival
HV / commissioning technicianAround 2031 onwardSTEADYHV authorisation, GWO BST, Sea Survival
// PLAN YOUR MOVE
Experienced technicians

This is far off and not yet a final contract. Keep offshore installation and rigging experience current, and watch for the project name and contract signing.

New to wind

Use the time to get GWO BST and BTT and basic offshore training. Dogger Bank C and other nearer projects are better places to start.