Hornsea 3: Seaway7 starts laying array cables at Ørsted's 2.9 GW UK wind farm

// WHAT HAPPENED

Seaway7 has started installing inter-array cables at Ørsted's Hornsea 3 offshore wind farm in the UK. In total it will lay 500 km of cable. The cables will connect 197 turbines to two offshore converter stations.

Seaway7 is using its cable-laying vessel Seaway Phoenix. The walk-to-work vessel Seaway Moxie supports the campaign. Hellenic and Prysmian supply the array cables. JDR Cable Systems handles cable testing and termination.

Ørsted's Hornsea 3 managing director, Luke Bridgman, said the project has worked on its array cables for almost five years, and that this is a key step for construction.

Hornsea 3 is Ørsted's first European HVDC project. It is the third gigawatt-scale wind farm in the Hornsea zone, after the 1.2 GW Hornsea 1 and the 1.4 GW Hornsea 2. The 2.9 GW wind farm will use 197 Siemens Gamesa SG 14-236 DD turbines.

// WHAT IT MEANS FOR JOBS
PHASE NOW
Array cable installation
HIRING WINDOW
Now – 2027 for cable and termination work · turbine installation and commissioning after that (estimate)
PLATFORM
Siemens Gamesa SG 14-236 DD
ROUGH SCALE
Estimate: 80–150 people across cable, termination and testing crews · 12–18 months
WORKFORCE EFFECT
Mixed: new demand + crews moving across
TIMELINE · WHEN THE WORK HAPPENS
H2 26 ▼ NOW
H1 27
H2 27
H1 28
H2 28
H1 29
H2 29
H1 30
H2 30
H1 31
H2 31
H1 32
H2 32
H1 33
H2 33
H1 34
H2 34
H1 35
H2 35
H1 36
H2 36
H1 37
H2 37
H1 38
H2 38
H1 39
H2 39
H1 40
H2 40
H1 41
H2 41
H1 42
H2 42
H1 43
H2 43
H1 44
H2 44
H1 45
H2 45
H1 46
H2 46
H1 47
H2 47
H1 48
H2 48
H1 49
H2 49
H1 50
H2 50
Array cable installation (Seaway7)
confirmed
Cable termination and testing (JDR)
planned
Turbine installation and commissioning
planned
Operations and maintenance
long-term

Solid bar = confirmed · outlined = planned · blue = long-term jobs

ROLES NEEDED
ROLEWHENDEMANDCERTIFICATES THAT HELP
Cable termination / HV technicianNow – 2027MEDIUMGWO BST, BTT, HV authorisation, OPITO / sea survival
Rigger / banksman (cable and vessel work)Now – 2027MEDIUMGWO BST, Slinger Signaller, offshore medical
Commissioning technician (LV / HV)2027 – 2028MEDIUMGWO BST, BTT, HV authorisation
Turbine installation technicianLater, when turbine work startsSTEADYGWO BST, BTT, ART, Sea Survival
// PLAN YOUR MOVE
Experienced techs

Watch for HV termination, testing and commissioning roles. Contact JDR, Ørsted contractors and Siemens Gamesa early.

New to wind

Get GWO BST and sea survival now. Turbine work is still ahead, and entry roles will open more as installation grows.

Looking for stability

A 2.9 GW site means long-term O&M work in the UK from the late 2020s. Aim at service roles for that.

Source: Offshore Wind (offshorewind.biz) · Scale figures are rough estimates from field experience, not official numbers.