·OFFSHORE ·TAIWAN ·FOUNDATION INSTALLATION (SUBSTATION ENERGISED) STRONG SIGNAL

Fengmiao 1: Taiwan offshore substation energised, turbine foundations continue

// WHAT HAPPENED

The offshore substation at Fengmiao 1 in Taiwan was energised in October. Developer Copenhagen Offshore Partners (COP), working for Copenhagen Infrastructure Partners, says the transmission system is now fully online. The project is still on track for grid connection by the end of 2027.

CSBC-DEME Wind Engineering installed the substation foundation and topside in August with the heavy-lift vessel Green Jade. Jan De Nul pulled the two export cables into the substation, which finished the offshore cable link. The 8,000-tonne jacket and 3,400-tonne topside were built by Semco Maritime and PTSC M&C.

Turbine foundation installation is still going. The team uses weather windows when they come. The wind farm will have 33 Vestas V236-15.0 MW turbines on three-legged jacket foundations. The pin piles for these were installed this summer.

The source does not give dates for turbine installation.

// WHAT IT MEANS FOR JOBS
PHASE NOW
Foundation installation (substation energised)
HIRING WINDOW
Turbine installation and commissioning likely 2027 · O&M from 2028 (estimate)
PLATFORM
Vestas V236-15.0 MW
ROUGH SCALE
Estimate: 60–100 people for turbine installation and commissioning · about 9–12 months
WORKFORCE EFFECT
Crews moving across
TIMELINE · WHEN THE WORK HAPPENS
H2 26 ▼ NOW
H1 27
H2 27
H1 28
H2 28
H1 29
H2 29
H1 30
H2 30
Substation installed and energised
confirmed
Turbine foundation installation
planned
Turbine installation and commissioning
planned
Grid connection target
confirmed
Operations and maintenance
long-term

Solid bar = confirmed · outlined = planned · blue = long-term jobs

ROLES NEEDED
ROLEWHENDEMANDCERTIFICATES THAT HELP
Turbine installation technician (mechanical)2027MEDIUMGWO BST, BTT, Sea Survival, offshore medical
Rigger / banksman2026-H2 – 2027MEDIUMGWO BST, Slinger Signaller, Rigging
HV / commissioning technician2027MEDIUMHV authorisation, GWO BST, Sea Survival
Service technician2028 onwardSTEADYGWO BST, BTT, offshore survival
// PLAN YOUR MOVE
Experienced technicians

Taiwan offshore work is in progress. Check with the installation contractors and Vestas about 2027 turbine installation and commissioning roles.

New to wind

Get GWO BST and offshore survival training first. Entry roles on this project are likely to be few, so apply for assistant or logistics roles.

Looking for stability

Plan for service roles after grid connection in 2028. Long-term O&M work is usually more stable than installation work.

Source: Offshore Wind (offshorewind.biz) · Scale figures are rough estimates from field experience, not official numbers.