Hornsea 3: Ørsted prepares turbine installation at the 2.9 GW UK offshore wind farm

// WHAT HAPPENED

Hornsea 3 in the UK is moving towards turbine installation. Ørsted says blades, nacelles and tower sections for the 197 Siemens Gamesa SG 14-236 DD turbines are at Able Seaton Port in northeast England. The first parts arrived in July 2026. Since then, the port team has stored them and has been pre-assembling tower sections before load-out.

DEME's jack-up vessel Norse Energi is at the port. The project's Notice to Mariners of 9 November says Norse Energi mobilised from Teesport that day. Cadeler's Wind Pace is due to mobilise from Hull on 15 November. The commissioning vessel IWS Seawalker and support vessels Fob Swath 9 and Fob Swath 10 leave Hull on the same date.

The notice says turbine installation and commissioning will run until November 2027.

Other work is already under way. The first monopile went in during May. Both offshore converter stations are installed, the second one in September. Seaway7 began laying inter-array cables this month. The 2.9 GW site lies about 120 km off Norfolk.

// WHAT IT MEANS FOR JOBS
PHASE NOW
Turbine installation starting (port preparation and vessel mobilisation)
HIRING WINDOW
Now – Q4 2027 · service roles after
PLATFORM
Siemens Gamesa SG 14-236 DD
ROUGH SCALE
Estimate: 150–250 people offshore and in port · about 12 months of turbine work
WORKFORCE EFFECT
Mixed: new demand + crews moving across
TIMELINE · WHEN THE WORK HAPPENS
H1 26
H2 26 ▼ NOW
H1 27
H2 27
H1 28
H2 28
H1 29
H2 29
H1 30
H2 30
Monopile installation starts (May 2026)
confirmed
Offshore converter stations installed
confirmed
Inter-array cable installation
planned
Turbine installation and commissioning (to Nov 2027)
confirmed
Operations and maintenance
long-term

Solid bar = confirmed · outlined = planned · blue = long-term jobs

ROLES NEEDED
ROLEWHENDEMANDCERTIFICATES THAT HELP
Turbine installation technician (mechanical)Now – Q4 2027MEDIUMGWO BST, BTT, Sea Survival, offshore medical
Commissioning technician (electrical)Early 2027 – Q4 2027MEDIUMGWO BST, BTT, electrical authorisation, LV/HV safety
Rigger / banksman / slinger signaller (port and vessel)Now – mid 2027STEADYGWO BST, Slinger Signaller, Rigger, ART
HV technician2027MEDIUMHV authorisation, GWO BST
// PLAN YOUR MOVE
Experienced technicians

Contact the installation and commissioning contractors early. Crews often move over from other finishing UK and European projects, so apply before the vessels begin full-rate work.

New to wind

Get GWO BST and offshore basics now. Port roles in pre-assembly and logistics at Able Seaton can be an easier way in than offshore work.

Looking for stability

Installation ends in late 2027. Aim for commissioning or service roles that can continue into operations and maintenance.

Source: Offshore Wind · Scale figures are rough estimates from field experience, not official numbers.