Hornsea 3: Ørsted prepares turbine installation at the 2.9 GW UK offshore wind farm
Hornsea 3 in the UK is moving towards turbine installation. Ørsted says blades, nacelles and tower sections for the 197 Siemens Gamesa SG 14-236 DD turbines are at Able Seaton Port in northeast England. The first parts arrived in July 2026. Since then, the port team has stored them and has been pre-assembling tower sections before load-out.
DEME's jack-up vessel Norse Energi is at the port. The project's Notice to Mariners of 9 November says Norse Energi mobilised from Teesport that day. Cadeler's Wind Pace is due to mobilise from Hull on 15 November. The commissioning vessel IWS Seawalker and support vessels Fob Swath 9 and Fob Swath 10 leave Hull on the same date.
The notice says turbine installation and commissioning will run until November 2027.
Other work is already under way. The first monopile went in during May. Both offshore converter stations are installed, the second one in September. Seaway7 began laying inter-array cables this month. The 2.9 GW site lies about 120 km off Norfolk.
Solid bar = confirmed · outlined = planned · blue = long-term jobs
| ROLE | WHEN | DEMAND | CERTIFICATES THAT HELP |
|---|---|---|---|
| Turbine installation technician (mechanical) | Now – Q4 2027 | MEDIUM | GWO BST, BTT, Sea Survival, offshore medical |
| Commissioning technician (electrical) | Early 2027 – Q4 2027 | MEDIUM | GWO BST, BTT, electrical authorisation, LV/HV safety |
| Rigger / banksman / slinger signaller (port and vessel) | Now – mid 2027 | STEADY | GWO BST, Slinger Signaller, Rigger, ART |
| HV technician | 2027 | MEDIUM | HV authorisation, GWO BST |
Contact the installation and commissioning contractors early. Crews often move over from other finishing UK and European projects, so apply before the vessels begin full-rate work.
Get GWO BST and offshore basics now. Port roles in pre-assembly and logistics at Able Seaton can be an easier way in than offshore work.
Installation ends in late 2027. Aim for commissioning or service roles that can continue into operations and maintenance.
Source: Offshore Wind · Scale figures are rough estimates from field experience, not official numbers.