·OFFSHORE ·TAIWAN ·FENGMIAO 1: FOUNDATION INSTALLATION; FENGMIAO 2: SUBSTATION CONTRACT AWARDED, PRE-FINANCIAL CLOSE MEDIUM SIGNAL

Fengmiao 2: Semco Maritime and PTSC M&C win offshore substation contract in Taiwan

// WHAT HAPPENED

CIP has signed a contract with Semco Maritime and PTSC M&C for the offshore substation of the 600 MW Fengmiao 2 wind project in Taiwan. It was announced on 16 November. The scope covers engineering, procurement, fabrication and installation. Semco Maritime handles engineering, procurement and installing the electrical systems. PTSC M&C builds the structural parts.

The same companies built the substation for the 495 MW Fengmiao 1 farm: a 3,400-tonne topside and an 8,000-tonne jacket. CSBC-DEME Wind Engineering installed it in August, and it was energised in October.

Fengmiao 1 is still in offshore construction, and turbine foundation installation continues. It will have 33 Vestas V236-15.0 MW turbines and should connect to the grid by the end of 2027.

Fengmiao 2 lies about 40 km off Taichung City. It won a place in Taiwan's Round 3.2 auction in August 2024. CIP aims for financial close by the end of Q2 2027 and grid connection by 2030.

// WHAT IT MEANS FOR JOBS
PHASE NOW
Fengmiao 1: foundation installation; Fengmiao 2: substation contract awarded, pre-financial close
HIRING WINDOW
Fengmiao 1 turbines: 2027 · Fengmiao 2 offshore work: 2028–2030
PLATFORM
Vestas V236-15.0 MW (Fengmiao 1)
ROUGH SCALE
Estimate: Fengmiao 1 turbine work about 80–120 people over 8–12 months; Fengmiao 2 offshore work starts later, size not yet known
WORKFORCE EFFECT
Crews moving across
TIMELINE · WHEN THE WORK HAPPENS
H2 26 ▼ NOW
H1 27
H2 27
H1 28
H2 28
H1 29
H2 29
H1 30
H2 30
Fengmiao 1 foundation and turbine installation
planned
Fengmiao 1 grid connection (end 2027)
confirmed
Fengmiao 2 financial close (by end Q2 2027)
planned
Fengmiao 2 substation fabrication and offshore construction
planned
Fengmiao 2 grid connection and operations
planned

Solid bar = confirmed · outlined = planned · blue = long-term jobs

ROLES NEEDED
ROLEWHENDEMANDCERTIFICATES THAT HELP
Turbine installation technician (Fengmiao 1)2027MEDIUMGWO BST, BTT, Sea Survival
Rigger / banksman2027 and 2029–2030MEDIUMGWO BST, Slinger Signaller, Basic Rigging
HV / commissioning technician2027 and 2029–2030MEDIUMHV authorisation, GWO BST
Substation electrical installer2029–2030LOWElectrical qualification, GWO BST, offshore medical
// PLAN YOUR MOVE
Experienced technicians

Fengmiao 1 turbine installation in 2027 is the nearer job. Watch for Fengmiao 2 contractor news once financial close is reached in 2027.

New to wind

Get GWO BST and BTT now. Fengmiao 2 is still years away, so use the time to build your certificates.

Looking for stability

Taiwan has several rounds of projects in the pipeline. Fengmiao 2 adds to the long-term local work, with grid connection set for 2030.

Source: Offshore Wind (offshorewind.biz) · Scale figures are rough estimates from field experience, not official numbers.