Oga–Katagami–Akita: first monopiles and towers arrive for Japan's 315 MW offshore wind farm

// WHAT HAPPENED

Preparations for the Oga–Katagami–Akita offshore wind farm (315 MW) off Akita Prefecture, Japan, are moving forward. The first batch of monopiles was delivered in September. The first turbine towers arrived on 29 October.

The monopiles are the first made in Japan for an offshore wind farm. JFE Engineering built them at its Kasaoka plant. Kajima Corporation holds the foundation contract from the developer, signed in October 2025.

The project will use 21 Vestas V236-15 MW turbines. Japan Offshore Marine, a joint venture of DEME and Penta-Ocean Construction, will install them with the jack-up vessel Sea Challenger in H2 2027. Offshore construction starts in spring 2027.

A balance of plant contract was awarded this month to a joint venture of JFE Engineering and Akita Maritime Service. It covers maintenance of the foundations, subsea cables, onshore substation and related grid assets, but not the turbines. Commercial operation is expected in mid-2028.

// WHAT IT MEANS FOR JOBS
PHASE NOW
Component deliveries and port preparation before offshore construction
HIRING WINDOW
Spring 2027 – mid-2028 · O&M from 2028
PLATFORM
Vestas V236-15 MW
ROUGH SCALE
Estimate: 60–100 people on installation and commissioning · about 12 months, mostly local and contractor crews
WORKFORCE EFFECT
Mixed: new demand + crews moving across
TIMELINE · WHEN THE WORK HAPPENS
H2 26 ▼ NOW
H1 27
H2 27
H1 28
H2 28
H1 29
H2 29
H1 30
H2 30
Monopile and tower deliveries
confirmed
Offshore construction starts (spring 2027)
confirmed
Turbine installation with Sea Challenger
confirmed
Commissioning and start of commercial operation (mid-2028)
planned
Operations and maintenance
long-term

Solid bar = confirmed · outlined = planned · blue = long-term jobs

ROLES NEEDED
ROLEWHENDEMANDCERTIFICATES THAT HELP
Offshore installation technician2027-H2MEDIUMGWO BST, BTT, Sea Survival, offshore medical
Rigger / banksman2027-H1 – 2027-H2MEDIUMGWO Slinger Signaller, BST, Advanced Rigging
HV / commissioning technician2028-H1MEDIUMHV authorisation, GWO BST, BTT
Service technician2028-H2 onwardSTEADYGWO BST, BTT, ART, OEM Vestas training
// PLAN YOUR MOVE
Experienced offshore techs

Japan is a young offshore market. If you have V236 or jack-up installation experience, watch DEME and Japan Offshore Marine for 2027 openings.

New to wind

Get GWO BST and BTT first. Expect the first offshore roles to go to people with offshore experience, and language or local requirements may apply.

Looking for stability

Long-term service work after mid-2028 is the steadier option. The balance of plant maintenance contract is a sign that local O&M jobs will follow.

Source: Offshore Wind (offshorewind.biz) · Scale figures are rough estimates from field experience, not official numbers.