LanWin beta: Smulders to build the jacket for TenneT's 2 GW North Sea converter platform

// WHAT HAPPENED

Eiffage Smulders (part of Eiffage Métal) has won a subcontract from Dragados Offshore to build the jacket foundation for the LanWin beta offshore converter platform. The platform is part of LanWin2, a 2 GW HVDC grid connection in the German North Sea for TenneT.

Work on the platform is planned to start in early 2027, with load-out expected in 2030. Smulders will fabricate the jacket in Belgium and Poland. Final assembly and load-out will take place in the Netherlands.

LanWin2 is due for commissioning in 2031. It belongs to TenneT's 2GW programme, which aims to standardise offshore grid connections.

Other work is already moving. Dragados Offshore cut the first steel for the converter platform in September 2025, at its yards in Italy and the United Arab Emirates. Nexans holds the contract for 250 km of 525 kV HVDC XLPE export cable, and began making the subsea cable in October 2026.

// WHAT IT MEANS FOR JOBS
PHASE NOW
Fabrication of cable and platform components (jacket work starts 2027)
HIRING WINDOW
Fabrication jobs 2027–2030 · offshore installation and HV commissioning about 2030–2031
ROUGH SCALE
Estimate: yard fabrication is a large job in steel yards. Offshore installation and commissioning of the platform needs roughly 50–100 people over 6–12 months around 2030–2031.
WORKFORCE EFFECT
Crews moving across
TIMELINE · WHEN THE WORK HAPPENS
H2 25
H1 26
H2 26 ▼ NOW
H1 27
H2 27
H1 28
H2 28
H1 29
H2 29
H1 30
H2 30
H1 31
H2 31
First steel cut (Dragados Offshore yards)
confirmed
Subsea cable manufacturing (Nexans)
confirmed
Jacket fabrication, Belgium and Poland, then assembly in the Netherlands
planned
Load-out of the jacket
planned
Commissioning of LanWin2
planned

Solid bar = confirmed · outlined = planned · blue = long-term jobs

ROLES NEEDED
ROLEWHENDEMANDCERTIFICATES THAT HELP
Structural/mechanical fitter (yard fabrication and assembly)2027–2030MEDIUMGWO BST, welding or fitting trade certificates
Rigger / banksman (load-out and lifting)2030STEADYGWO BST, Slinger Signaller
HV / commissioning technician (converter platform)2030–2031MEDIUMGWO BST, BTT, HV authorisation, offshore medical, OPITO BOSIET
HSE advisor / supervisor2027–2031STEADYGWO BST, NEBOSH or similar
// PLAN YOUR MOVE
Experienced technicians

Converter platform work needs HV and commissioning skills. Offshore HVDC experience will be worth more around 2030–2031. Keep your HV authorisation and offshore certificates valid.

New to wind

Nothing is hiring for technicians yet. Get GWO BST now and look at fabrication yards in Belgium, Poland and the Netherlands for fitter and assistant roles from 2027.

Looking for stability

This is a multi-year project, with yard work to 2030 and commissioning in 2031. It suits you if you want long fabrication work, but crews will mostly move across from other projects.