·OFFSHORE ·POLAND ·SUBSTATION TOPSIDE INSTALLATION AND START OF HOOK-UP AND COMMISSIONING PREP STRONG SIGNAL

Bałtyk 2 & 3: Searenergy wins hook-up and commissioning work on Polish offshore substations

// WHAT HAPPENED

The Equinor and Polenergia joint venture has given Searenergy Poland a contract for hook-up and commissioning (HUC) of the offshore substations at Bałtyk 2 and Bałtyk 3. The firm will also support commissioning of the 100 turbines across the two wind farms.

Searenergy will supply key commissioning staff for onshore and offshore work, plus engineering, HSE services and on-site procurement support. It will also do corrective maintenance on transition pieces at the O&M base in Łeba, to prepare them for turbine installation.

The two farms are 720 MW each (1.44 GW total), built 37 km and 22 km off the Polish coast. Each will have 50 Siemens Gamesa SG 14-236 DD turbines of 14.4 MW.

All 100 turbine foundations and two substation jackets are already installed. Heerema finished that campaign in September with the crane vessel Thialf. Heerema returns this winter to lift the Bałtyk 2 substation topside. The Bałtyk 3 topside follows in summer 2027. First power is expected in 2027, and full commercial operation in 2028.

// WHAT IT MEANS FOR JOBS
PHASE NOW
Substation topside installation and start of hook-up and commissioning prep
HIRING WINDOW
Now – 2027 (turbine and substation commissioning) · O&M from 2028
PLATFORM
Siemens Gamesa SG 14-236 DD (14.4 MW)
ROUGH SCALE
Estimate: 40–80 commissioning and HUC people at peak · about 12–18 months
WORKFORCE EFFECT
Mixed: new demand + crews moving across
TIMELINE · WHEN THE WORK HAPPENS
H1 26
H2 26 ▼ NOW
H1 27
H2 27
H1 28
H2 28
H1 29
H2 29
H1 30
H2 30
Foundations and substation jackets installed
confirmed
Bałtyk 2 substation topside installation
confirmed
Bałtyk 3 substation topside installation
confirmed
Hook-up and commissioning, turbine commissioning support
planned
First power 2027, full commercial operation 2028
planned
Operations and maintenance from Łeba base
long-term

Solid bar = confirmed · outlined = planned · blue = long-term jobs

ROLES NEEDED
ROLEWHENDEMANDCERTIFICATES THAT HELP
HV / commissioning technician (substation)2026-H2 – 2027MEDIUMGWO BST, BTT, HV authorisation, offshore medical
Turbine commissioning technician2027 – 2028MEDIUMGWO BST, BTT, Sea Survival, OEM training
Mechanical / TP corrective maintenance technician2026-H2 – 2027STEADYGWO BST, BTT, ART
Rigger / banksman2027STEADYGWO BST, Slinger Signaller, Sea Survival
// PLAN YOUR MOVE
Experienced

HV and commissioning people with offshore substation experience are the target. Contact Searenergy Poland and the main contractors early, as the work starts this winter.

New to wind

Get GWO BST and Sea Survival now. Poland's Baltic projects will need many support roles as turbine commissioning starts in 2027.

Looking for stability

Full operation in 2028 and the Łeba O&M base point to service jobs. Aim for a turbine service role there after commissioning.

Source: Offshore Wind (offshorewind.biz) · Scale figures are rough estimates from field experience, not official numbers.