Zeevonk Phase I: Siemens Gamesa to supply 69 SG 15-236 turbines for Dutch 1 GW offshore wind farm
Vattenfall and Copenhagen Infrastructure Partners (CIP), through their joint venture, have chosen Siemens Gamesa for Zeevonk Phase I off the Dutch coast. The order covers 69 SG 15-236 turbines. Each is rated 15 MW, with a boost of up to 15.5 MW, so the farm reaches just over 1 GW.
The turbines have a 236 m rotor, 115 m blades and a tip height of 263 m. Some will use the GreenerTower and RecyclableBlade solutions. Siemens Gamesa's website says serial production of this model starts in 2028.
A service and warranty agreement was signed together with the supply deal. CIP says these are the two largest contracts, so the project is moving towards a final investment decision.
Other suppliers are already named. TKF has the inter-array cables, DEME has the foundation and turbine installation vessels, Boskalis has cable installation, and EEW SPC will make 69 monopiles. Phase I is to deliver 1 GW by 2029. Zeevonk II follows in 2032 with another 1 GW and 500 MW of system integration.
Solid bar = confirmed · outlined = planned · blue = long-term jobs
| ROLE | WHEN | DEMAND | CERTIFICATES THAT HELP |
|---|---|---|---|
| Turbine installation technician (mechanical) | 2028-H2 – 2029 | MEDIUM | GWO BST, BTT, Sea Survival, offshore medical |
| Rigger / Slinger Signaller | 2028-H2 – 2029 | MEDIUM | GWO BST, Slinger Signaller, Banksman, rigging experience |
| Electrical / commissioning technician | 2029 | MEDIUM | GWO BST, BTT, EuP or HV authorisation |
| Service technician (Siemens Gamesa fleet) | 2029 onwards | STEADY | GWO BST, BTT, OEM training |
Installation is about two years away. Get offshore installation or SG 14-222 / 15-236 type experience on your CV, and watch for DEME and Siemens Gamesa recruitment in 2027–2028.
Get GWO BST and Sea Survival now. Use the time before 2028 to build experience onshore or on other projects.
The long service and warranty agreement means service roles from about 2029. These are steadier than installation work.
Source: Offshore Wind · Scale figures are rough estimates from field experience, not official numbers.