Zeevonk Phase I: Siemens Gamesa to supply 69 SG 15-236 turbines for Dutch 1 GW offshore wind farm

// WHAT HAPPENED

Vattenfall and Copenhagen Infrastructure Partners (CIP), through their joint venture, have chosen Siemens Gamesa for Zeevonk Phase I off the Dutch coast. The order covers 69 SG 15-236 turbines. Each is rated 15 MW, with a boost of up to 15.5 MW, so the farm reaches just over 1 GW.

The turbines have a 236 m rotor, 115 m blades and a tip height of 263 m. Some will use the GreenerTower and RecyclableBlade solutions. Siemens Gamesa's website says serial production of this model starts in 2028.

A service and warranty agreement was signed together with the supply deal. CIP says these are the two largest contracts, so the project is moving towards a final investment decision.

Other suppliers are already named. TKF has the inter-array cables, DEME has the foundation and turbine installation vessels, Boskalis has cable installation, and EEW SPC will make 69 monopiles. Phase I is to deliver 1 GW by 2029. Zeevonk II follows in 2032 with another 1 GW and 500 MW of system integration.

// WHAT IT MEANS FOR JOBS
PHASE NOW
Contracting before final investment decision
HIRING WINDOW
Hiring mainly 2028 – 2029 (installation and commissioning) · service from ~2029 · again 2031 – 2032 for Phase II
PLATFORM
Siemens Gamesa SG 15-236 (15 MW, up to 15.5 MW)
ROUGH SCALE
Estimate: 100–180 people on turbine installation and commissioning · about 12–18 months, then a long-term service team
WORKFORCE EFFECT
Crews moving across
TIMELINE · WHEN THE WORK HAPPENS
H2 26 ▼ NOW
H1 27
H2 27
H1 28
H2 28
H1 29
H2 29
H1 30
H2 30
H1 31
H2 31
H1 32
H2 32
H1 33
H2 33
H1 34
H2 34
H1 35
H2 35
H1 36
H2 36
H1 37
H2 37
H1 38
H2 38
H1 39
H2 39
H1 40
H2 40
Turbine, service and foundation contracts
confirmed
Final investment decision (expected)
planned
Serial production of SG 15-236 starts
confirmed
Phase I offshore installation and commissioning
planned
Phase II (1 GW + 500 MW system integration)
confirmed
Operations and service
long-term

Solid bar = confirmed · outlined = planned · blue = long-term jobs

ROLES NEEDED
ROLEWHENDEMANDCERTIFICATES THAT HELP
Turbine installation technician (mechanical)2028-H2 – 2029MEDIUMGWO BST, BTT, Sea Survival, offshore medical
Rigger / Slinger Signaller2028-H2 – 2029MEDIUMGWO BST, Slinger Signaller, Banksman, rigging experience
Electrical / commissioning technician2029MEDIUMGWO BST, BTT, EuP or HV authorisation
Service technician (Siemens Gamesa fleet)2029 onwardsSTEADYGWO BST, BTT, OEM training
// PLAN YOUR MOVE
Experienced techs

Installation is about two years away. Get offshore installation or SG 14-222 / 15-236 type experience on your CV, and watch for DEME and Siemens Gamesa recruitment in 2027–2028.

New to wind

Get GWO BST and Sea Survival now. Use the time before 2028 to build experience onshore or on other projects.

Looking for stability

The long service and warranty agreement means service roles from about 2029. These are steadier than installation work.

Source: Offshore Wind · Scale figures are rough estimates from field experience, not official numbers.