BC-Wind: first monopiles land in Świnoujście as Windar gets tower deal

// WHAT HAPPENED

BC-Wind, the 390 MW Ocean Winds project in the Polish Baltic Sea, has reached a new step before offshore construction. On 28 October, the first monopile foundations arrived at Świnoujście Offshore Terminal. Ocean Winds says it is the first time a Polish installation port has received foundations this large. They will be stored there, then prepared for transport and installation at sea.

The project needs 27 monopiles: 26 for turbines and one for the offshore substation.

On 18 November, Windar signed an agreement with Siemens Gamesa. Windar will build and assemble towers for 26 SG 15-236 turbines at its Szczecin facility.

Ocean Winds plans to start foundation installation in the first half of 2027. Siemens Gamesa was chosen as turbine supplier in July 2025. Cadeler has the turbine installation contract and is due to do that work in 2028.

// WHAT IT MEANS FOR JOBS
PHASE NOW
Foundations logistics (monopiles in port, towers being contracted)
HIRING WINDOW
Port and foundation work H1 2027 · turbine installation 2028 · service from about 2028–2029
PLATFORM
Siemens Gamesa SG 15-236
ROUGH SCALE
Estimate: 40–70 technicians at peak turbine installation · about 6–9 months in 2028
WORKFORCE EFFECT
Mixed: new demand + crews moving across
TIMELINE · WHEN THE WORK HAPPENS
H2 26 ▼ NOW
H1 27
H2 27
H1 28
H2 28
H1 29
H2 29
H1 30
H2 30
Monopiles arrive at Świnoujście
confirmed
Foundation installation
planned
Turbine installation (Cadeler)
confirmed
Operations and maintenance
long-term

Solid bar = confirmed · outlined = planned · blue = long-term jobs

ROLES NEEDED
ROLEWHENDEMANDCERTIFICATES THAT HELP
Installation technician (mechanical)2028MEDIUMGWO BST, BTT, Sea Survival
Rigger / banksman2027–2028MEDIUMSlinger Signaller, GWO BST, offshore medical
HV / commissioning technicianLate 2028 onwardsMEDIUMEuP / HV authorisation, GWO BST
Service technicianFrom about 2029STEADYGWO BST, BTT, Sea Survival
// PLAN YOUR MOVE
Experienced technicians

Turbine work is in 2028. Watch for Cadeler and Siemens Gamesa crew calls in 2027, and plan to be free when your current project ends.

New to wind

Get GWO BST and offshore basics now. Entry roles in Poland may open in 2027–2028 with port and installation support.

Looking for stability

Aim for service roles. The wind farm will need O&M crews for years after installation ends.

Source: Offshore Wind · Scale figures are rough estimates from field experience, not official numbers.