Dogger Bank: about 150 turbines installed, remediation work under way at phase A
SSE gave an update on Dogger Bank (3.6 GW) in its half-year results on 18 November. About 150 turbines are installed across the three phases, and about 100 are commissioned.
At Dogger Bank A (1.2 GW), some turbines from the first installation campaign need extra work to meet quality and reliability standards. Remediation is under way. Most turbines there are commissioned. SSE expects the capacity to be "substantially available" by the end of Q1 2027, with final commissioning done by the end of Q3 2027.
At Dogger Bank B, 52 of 95 turbines are installed, and the pace is well ahead of phase A. Most of its 1.2 GW should be available in H1 2027.
At Dogger Bank C, foundations are in place, the inter-array cables are installed, and testing and commissioning are in progress. Cadeler's Wind Apex will join Seaway Ventus in Q3 2027 for turbine installation.
SSE also said Berwick Bank B (1.4 GW) targets a final investment decision in H2 2027. Preparatory offshore construction could start in 2028.
Solid bar = confirmed · outlined = planned · blue = long-term jobs
| ROLE | WHEN | DEMAND | CERTIFICATES THAT HELP |
|---|---|---|---|
| Remediation / mechanical technician (phase A) | Now – Q1 2027 | MEDIUM | GWO BST, BTT, OPITO / offshore medical |
| Installation / commissioning technician (phase B) | Now – mid 2027 | MEDIUM | GWO BST, BTT, Sea Survival |
| HV / commissioning technician | 2027 (B final, C start) | MEDIUM | HV authorisation, GWO BST |
| Rigger / banksman for installation vessels | Q3 2027 onward (phase C) | STEADY | Slinger Signaller, GWO BST, GWO Working at Heights |
Phase A remediation and phase B commissioning run at the same time. Contact contractors now. Phase C turbine installation in Q3 2027 is the next wave.
Get GWO BST and BTT and an offshore medical first. Phase C and later O&M are better entry points than the busy remediation work.
Aim at the long-term operations and maintenance roles that follow commissioning in late 2027. Berwick Bank B is further away, with preparatory work from 2028.