Dogger Bank: about 150 turbines installed, remediation work under way at phase A

// WHAT HAPPENED

SSE gave an update on Dogger Bank (3.6 GW) in its half-year results on 18 November. About 150 turbines are installed across the three phases, and about 100 are commissioned.

At Dogger Bank A (1.2 GW), some turbines from the first installation campaign need extra work to meet quality and reliability standards. Remediation is under way. Most turbines there are commissioned. SSE expects the capacity to be "substantially available" by the end of Q1 2027, with final commissioning done by the end of Q3 2027.

At Dogger Bank B, 52 of 95 turbines are installed, and the pace is well ahead of phase A. Most of its 1.2 GW should be available in H1 2027.

At Dogger Bank C, foundations are in place, the inter-array cables are installed, and testing and commissioning are in progress. Cadeler's Wind Apex will join Seaway Ventus in Q3 2027 for turbine installation.

SSE also said Berwick Bank B (1.4 GW) targets a final investment decision in H2 2027. Preparatory offshore construction could start in 2028.

// WHAT IT MEANS FOR JOBS
PHASE NOW
Turbine installation (B), remediation and commissioning (A), cable testing (C)
HIRING WINDOW
Now – Q3 2027 · O&M from 2027
ROUGH SCALE
Estimate: 100–200 people across phases A, B and C · about 10–12 months of peak work
WORKFORCE EFFECT
Mixed: new demand + crews moving across
TIMELINE · WHEN THE WORK HAPPENS
H2 26 ▼ NOW
H1 27
H2 27
H1 28
H2 28
H1 29
H2 29
H1 30
H2 30
Dogger Bank A remediation and commissioning
confirmed
Dogger Bank B turbine installation and commissioning
confirmed
Dogger Bank C turbine installation (Wind Apex joins Q3 2027)
confirmed
Berwick Bank B FID and preparatory offshore work
planned
Dogger Bank operations and maintenance
long-term

Solid bar = confirmed · outlined = planned · blue = long-term jobs

ROLES NEEDED
ROLEWHENDEMANDCERTIFICATES THAT HELP
Remediation / mechanical technician (phase A)Now – Q1 2027MEDIUMGWO BST, BTT, OPITO / offshore medical
Installation / commissioning technician (phase B)Now – mid 2027MEDIUMGWO BST, BTT, Sea Survival
HV / commissioning technician2027 (B final, C start)MEDIUMHV authorisation, GWO BST
Rigger / banksman for installation vesselsQ3 2027 onward (phase C)STEADYSlinger Signaller, GWO BST, GWO Working at Heights
// PLAN YOUR MOVE
Experienced technicians

Phase A remediation and phase B commissioning run at the same time. Contact contractors now. Phase C turbine installation in Q3 2027 is the next wave.

New to wind

Get GWO BST and BTT and an offshore medical first. Phase C and later O&M are better entry points than the busy remediation work.

Looking for stability

Aim at the long-term operations and maintenance roles that follow commissioning in late 2027. Berwick Bank B is further away, with preparatory work from 2028.

Source: Offshore Wind (offshorewind.biz) · Scale figures are rough estimates from field experience, not official numbers.