·OFFSHORE ·GERMANY ·FOUNDATIONS COMPLETE; TURBINE COMPONENTS IN PRODUCTION STRONG SIGNAL

Nordlicht I: all 68 foundations installed at Germany's largest offshore wind farm

// WHAT HAPPENED

DEME has finished the foundation work at Nordlicht I, Vattenfall's 980 MW offshore wind farm in the German North Sea, about 85 km north of Borkum. The last transition pieces are now in place. This follows the 68th monopile, which went in at the end of September.

DEME transported and installed the monopiles and transition pieces. EEW Special Pipe Constructions made the monopiles. CS Wind Offshore supplied the transition pieces.

The wind farm will use 68 Vestas V236-15.0 MW turbines. Cable production by TKF and tower production by Vestas are under way. The first tower sections have reached Esbjerg. Blade and nacelle production should start in the coming months.

Vattenfall expects commercial operation in 2028. Once running, Nordlicht I will be Germany's largest offshore wind farm. The second phase, the 630 MW Nordlicht II, is planned for 2029. Together the two make up a 1.6 GW cluster.

// WHAT IT MEANS FOR JOBS
PHASE NOW
Foundations complete; turbine components in production
HIRING WINDOW
Cable and turbine installation roles likely 2027 – 2028 · service roles from 2028
PLATFORM
Vestas V236-15.0 MW
ROUGH SCALE
Estimate: 100–180 people at peak for turbine installation and commissioning · about 12–18 months offshore work
WORKFORCE EFFECT
Crews moving across
TIMELINE · WHEN THE WORK HAPPENS
H1 26
H2 26 ▼ NOW
H1 27
H2 27
H1 28
H2 28
H1 29
H2 29
H1 30
H2 30
Foundation installation (68 monopiles and transition pieces)
confirmed
Cable, tower, blade and nacelle production
planned
Turbine installation and commissioning (estimate)
planned
Nordlicht I commercial operation
planned
Nordlicht II (630 MW) in operation
planned
Operations and maintenance
long-term

Solid bar = confirmed · outlined = planned · blue = long-term jobs

ROLES NEEDED
ROLEWHENDEMANDCERTIFICATES THAT HELP
Turbine installation technician (mechanical)2027-H2 – 2028MEDIUMGWO BST, BTT, Sea Survival, offshore medical
Rigger / banksman / slinger signaller2027-H2 – 2028MEDIUMSlinger Signaller, GWO BST, Sea Survival
HV / commissioning technician2028MEDIUMHV authorisation, GWO BST, Sea Survival
Service technician (V236)2028 onwardsSTEADYGWO BST, BTT, Vestas training
// PLAN YOUR MOVE
Experienced techs

Contact Vestas and its installation contractors in 2027. Work on V236 or other 15 MW turbines will count in your favour.

New to wind

Get GWO BST and Sea Survival now. Offshore jobs for this project are probably a year away, so you have time to prepare.

Looking for stability

Aim for service roles. Nordlicht I starts operating in 2028 and Nordlicht II follows in 2029, so long-term maintenance work should follow.

Source: Offshore Wind (offshorewind.biz) · Scale figures are rough estimates from field experience, not official numbers.