Nordseecluster B: first 10 monopiles arrive in Eemshaven ahead of 2027 foundation work

// WHAT HAPPENED

The first ten monopiles for Nordseecluster B, the second phase of RWE's German offshore wind project, have been unloaded at the port of Eemshaven in the Netherlands. They were made by China's Dajin Heavy Industry. Each one is about 81 m long and weighs around 1,350 tonnes.

In total, 60 monopiles will pass through Buss Ports' heavy-lift terminal in Eemshaven in 2026 and 2027. Nordseecluster B will add 900 MW. Together with phase A (660 MW), the cluster reaches about 1.6 GW. It lies roughly 50 km north of the island of Juist, and RWE builds it with Norges Bank Investment Management.

Nordseecluster A should be fully operational in early 2027. Foundation installation for phase B is due to begin next year, and the 60 turbines will be installed in 2028. Commercial operation is planned for early 2029. RWE is also building other large offshore projects, including Sofia, Vanguard East & West, Thor and OranjeWind.

// WHAT IT MEANS FOR JOBS
PHASE NOW
Foundation components arriving at port (marshalling); phase A still being completed
HIRING WINDOW
Port work now – 2027 · turbine installation crews 2028 · service from 2029
ROUGH SCALE
Estimate: 80–150 people for 60 turbines · about 8–12 months in 2028; smaller port and foundation crews in 2027
WORKFORCE EFFECT
Crews moving across
TIMELINE · WHEN THE WORK HAPPENS
H2 26 ▼ NOW
H1 27
H2 27
H1 28
H2 28
H1 29
H2 29
H1 30
H2 30
Monopile deliveries to Eemshaven
confirmed
Nordseecluster A fully operational
confirmed
Nordseecluster B foundation installation
planned
Nordseecluster B turbine installation (60 turbines)
confirmed
Nordseecluster B operation and maintenance
long-term

Solid bar = confirmed · outlined = planned · blue = long-term jobs

ROLES NEEDED
ROLEWHENDEMANDCERTIFICATES THAT HELP
Rigger / banksman (port and vessel)2026–2027STEADYGWO BST, Slinger Signaller, GWO Basic Technical Training
Turbine installation technician (mechanical)2028MEDIUMGWO BST, BTT, Sea Survival, ART
HV / commissioning technicianLate 2028 – 2029MEDIUMEuP / HV authorisation, GWO BST, BTT
Offshore service technicianFrom 2029STEADYGWO BST, BTT, Sea Survival, OPITO
// PLAN YOUR MOVE
Experienced technicians

Phase A finishes in 2027 and phase B turbine work starts in 2028. Crews will mostly move across, so talk to contractors early about the 2028 installation window.

New to wind

Get GWO BST and BTT now, plus Sea Survival. Entry roles such as rigger, banksman or assistant are the usual way in before 2028.

Looking for stability

Long-term service work starts with commercial operation in early 2029. Watch for RWE and service-provider vacancies in late 2028.