← ALL WIND NEWS

·OFFSHORE ·NETHERLANDS, GERMANY ·PORT MARSHALLING AND FOUNDATION INSTALLATION (ORANJEWIND); FOUNDATION DELIVERY (NORDSEECLUSTER B) STRONG SIGNAL

Eemshaven port starts work for Nordseecluster B and OranjeWind: 113 Vestas turbines to come

// WHAT HAPPENED

Buss Terminal Eemshaven in the Netherlands has begun marshalling work for two RWE-linked offshore wind farms: Nordseecluster B (900 MW, Germany) and OranjeWind (795 MW, Netherlands).

For Nordseecluster B, the terminal will handle 60 monopiles and their secondary steel. Each is about 81 m long and weighs up to 1,350 tonnes. RWE said the first 10 have arrived. The rest will come during 2026 and 2027. Foundation installation starts in 2027, turbine installation in 2028, and commercial operation is planned for early 2029. The turbines are 60 Vestas V236-15.0 MW.

For OranjeWind, the terminal will be the marshalling and pre-assembly base for 53 Vestas V236-15 MW turbines. Load-out is expected to start in spring 2027. Jan De Nul is installing the foundations, and the first monopile went in during September 2026. Turbine installation is planned for 2027, with full commissioning in early 2028.

Both projects use the new Heavy Duty Quay. This is the first time the terminal handles turbines and foundations side by side.

// WHAT IT MEANS FOR JOBS
PHASE NOW
Port marshalling and foundation installation (OranjeWind); foundation delivery (Nordseecluster B)
HIRING WINDOW
Spring 2027 – early 2028 (OranjeWind pre-assembly and installation) · again 2028 – early 2029 (Nordseecluster B)
PLATFORM
Vestas V236-15 MW
ROUGH SCALE
Estimate: 60–100 people at peak for pre-assembly, installation and commissioning · about 12 months for OranjeWind, then about 12 months for Nordseecluster B
WORKFORCE EFFECT
Crews moving across
TIMELINE · WHEN THE WORK HAPPENS
H2 26 ▼ NOW
H1 27
H2 27
H1 28
H2 28
H1 29
H2 29
OranjeWind foundation installation
confirmed
OranjeWind turbine load-out and installation
confirmed
OranjeWind full commissioning
planned
Nordseecluster B foundation installation
confirmed
Nordseecluster B turbine installation
confirmed
Nordseecluster B commercial operation
planned
Operations and maintenance
long-term

Solid bar = confirmed · outlined = planned · blue = long-term jobs

ROLES NEEDED
ROLEWHENDEMANDCERTIFICATES THAT HELP
Pre-assembly / installation technicianSpring 2027 – 2027 H2, then 2028MEDIUMGWO BST, BTT, Vestas or OEM training helps
Rigger / banksman / slinger signaller2027 (quay and load-out), 2028MEDIUMSlinger Signaller, GWO BST, Working at Heights
HV / commissioning technicianLate 2027 – early 2028, then 2028 – early 2029MEDIUMHV authorisation, GWO BST, BTT, offshore medical, sea survival
Service technicianFrom 2028STEADYGWO BST, BTT, offshore sea survival
// PLAN YOUR MOVE
Experienced technicians

OranjeWind turbine work comes first, with Nordseecluster B following in 2028. Contact Vestas and its installation contractors early. Experience on V236 turbines and pre-assembly will help.

New to wind

Get GWO BST and BTT done during 2026–27. Port pre-assembly work is a realistic way in before offshore installation starts.

Looking for stability

Think about service roles. Both farms will need O&M crews from 2028 and 2029, for many years.

Source: Offshore Wind (offshorewind.biz) · Scale figures are rough estimates from field experience, not official numbers.