Eemshaven port starts work for Nordseecluster B and OranjeWind: 113 Vestas turbines to come
Buss Terminal Eemshaven in the Netherlands has begun marshalling work for two RWE-linked offshore wind farms: Nordseecluster B (900 MW, Germany) and OranjeWind (795 MW, Netherlands).
For Nordseecluster B, the terminal will handle 60 monopiles and their secondary steel. Each is about 81 m long and weighs up to 1,350 tonnes. RWE said the first 10 have arrived. The rest will come during 2026 and 2027. Foundation installation starts in 2027, turbine installation in 2028, and commercial operation is planned for early 2029. The turbines are 60 Vestas V236-15.0 MW.
For OranjeWind, the terminal will be the marshalling and pre-assembly base for 53 Vestas V236-15 MW turbines. Load-out is expected to start in spring 2027. Jan De Nul is installing the foundations, and the first monopile went in during September 2026. Turbine installation is planned for 2027, with full commissioning in early 2028.
Both projects use the new Heavy Duty Quay. This is the first time the terminal handles turbines and foundations side by side.
Solid bar = confirmed · outlined = planned · blue = long-term jobs
| ROLE | WHEN | DEMAND | CERTIFICATES THAT HELP |
|---|---|---|---|
| Pre-assembly / installation technician | Spring 2027 – 2027 H2, then 2028 | MEDIUM | GWO BST, BTT, Vestas or OEM training helps |
| Rigger / banksman / slinger signaller | 2027 (quay and load-out), 2028 | MEDIUM | Slinger Signaller, GWO BST, Working at Heights |
| HV / commissioning technician | Late 2027 – early 2028, then 2028 – early 2029 | MEDIUM | HV authorisation, GWO BST, BTT, offshore medical, sea survival |
| Service technician | From 2028 | STEADY | GWO BST, BTT, offshore sea survival |
OranjeWind turbine work comes first, with Nordseecluster B following in 2028. Contact Vestas and its installation contractors early. Experience on V236 turbines and pre-assembly will help.
Get GWO BST and BTT done during 2026–27. Port pre-assembly work is a realistic way in before offshore installation starts.
Think about service roles. Both farms will need O&M crews from 2028 and 2029, for many years.
Source: Offshore Wind (offshorewind.biz) · Scale figures are rough estimates from field experience, not official numbers.