IJmuiden Ver Beta: NKT starts HVDC cable production for the Dutch 2 GW grid link

// WHAT HAPPENED

NKT has started production of the HVDC cable systems for TenneT's IJmuiden Ver Beta offshore grid connection in the Netherlands. The cable uses low-carbon aluminium wire rod from Hydro REDUXA, supplied under a long-term deal signed in 2024. The rod's carbon footprint is 3.7 kg CO₂e per kg, about 40% below the European average.

TenneT awarded the project to NKT in 2023. It is a 525 kV XLPE HVDC system with 2 GW capacity. It will carry power from the Zeevonk offshore wind farm, developed by Vattenfall and Copenhagen Infrastructure Partners, to the Dutch grid on land. TenneT calls it its first standardised 2 GW, 525 kV HVDC offshore connection.

Other parts of the project are moving too. Earlier this year, Heerema Fabrication Group finished the first structural element of the jacket foundation for the transformer platform at its Vlissingen yard. This month, TenneT said underground cable installation at Maasvlakte in Rotterdam, serving three new offshore wind sites including this one, is nearly complete.

// WHAT IT MEANS FOR JOBS
PHASE NOW
Cable manufacturing and platform fabrication; onshore cabling nearly done
HIRING WINDOW
Cable and platform installation likely 2027–2028 · commissioning after that
ROUGH SCALE
Estimate: 40–80 offshore and HV people for cable laying, platform hook-up and commissioning · about 12–18 months of work
WORKFORCE EFFECT
Crews moving across
TIMELINE · WHEN THE WORK HAPPENS
H1 26
H2 26 ▼ NOW
H1 27
H2 27
H1 28
H2 28
H1 29
H2 29
H1 30
H2 30
H1 31
H2 31
H1 32
H2 32
H1 33
H2 33
H1 34
H2 34
H1 35
H2 35
HVDC cable production (NKT)
planned
Transformer platform jacket fabrication
planned
Offshore cable and platform installation
planned
Grid connection operation and maintenance
long-term

Solid bar = confirmed · outlined = planned · blue = long-term jobs

ROLES NEEDED
ROLEWHENDEMANDCERTIFICATES THAT HELP
HV cable jointer / termination technician2027–2028MEDIUMGWO BST, HV authorisation, jointing qualification
HV commissioning technician2028MEDIUMGWO BST, BTT, EuP / HV authorisation
Rigger / banksman for platform hook-up2027–2028STEADYGWO BST, Slinger Signaller, OPITO
Mechanical fitter (platform)2027–2028STEADYGWO BST, BTT, OPITO
// PLAN YOUR MOVE
Experienced

If you have HVDC or cable jointing experience, watch for NKT, TenneT and platform contractors. Skilled HV people are in short supply.

New to wind

Get GWO BST and offshore basics now. Hiring for this job is still a year or more away, so you have time to prepare.

Looking for stability

Grid links run for decades. Aim for roles in HV commissioning or later operation and maintenance, not short installation jobs.

Source: Offshore Wind · Scale figures are rough estimates from field experience, not official numbers.