·OFFSHORE ·UNITED KINGDOM ·TURBINE INSTALLATION STARTING; JACKET FOUNDATIONS STILL BEING INSTALLED STRONG SIGNAL

Inch Cape: turbine installation starts off Scotland with Cadeler's Wind Mover

// WHAT HAPPENED

Turbine installation at Inch Cape, off the Angus coast in Scotland, has started. Cadeler's new installation vessel Wind Mover is doing the work.

A Notice to Mariners dated 27 October says the vessel will first jack up at the site in a safe haven position. Then it will go to the Port of Dundee to load components. AIS data shows Wind Mover reached the site on 30 October.

Acta Marine's service operations vessel Acta Hercules will support commissioning. The crew transfer vessels NOS Exceller and NOS Empowerer will support operations.

Installation and commissioning will continue until September 2027.

The wind farm will have 72 Vestas V236-15.0 MW turbines. They will sit on 54 monopiles and 18 jackets. All monopiles are in place, and jacket installation is under way.

Inch Cape is 1.1 GW and lies about 15 km offshore. First power is expected in late 2026. Full commercial operation is expected in 2027.

// WHAT IT MEANS FOR JOBS
PHASE NOW
Turbine installation starting; jacket foundations still being installed
HIRING WINDOW
Now – Q3 2027 · O&M from 2027
PLATFORM
Vestas V236-15.0 MW
ROUGH SCALE
Estimate: 60–100 people on installation and commissioning · about 11 months
WORKFORCE EFFECT
Mixed: new demand + crews moving across
TIMELINE · WHEN THE WORK HAPPENS
H1 26
H2 26 ▼ NOW
H1 27
H2 27
H1 28
H2 28
H1 29
H2 29
H1 30
H2 30
Monopile foundations installed
confirmed
Jacket foundation installation
confirmed
Turbine installation and commissioning
confirmed
First power
planned
Full commercial operation
planned
Operations and maintenance
long-term

Solid bar = confirmed · outlined = planned · blue = long-term jobs

ROLES NEEDED
ROLEWHENDEMANDCERTIFICATES THAT HELP
Offshore installation technician (mechanical)Now – Q3 2027MEDIUMGWO BST, BTT, Sea Survival, Offshore medical
Commissioning technician (electrical / HV)Late 2026 – Q3 2027MEDIUMGWO BST, HV authorisation, LV/HV switching, Offshore medical
Rigger / banksmanNow – Q3 2027STEADYGWO BST, Slinger Signaller, Rigging, Sea Survival
Service technician (O&M)From 2027STEADYGWO BST, BTT, ART, Sea Survival
// PLAN YOUR MOVE
Experienced technicians

Contact the installation and commissioning contractors now. Commissioning starts as the first turbines go up, and V236 experience helps.

New to wind

Get GWO BST and BTT first, plus Sea Survival and an offshore medical. Entry roles are more likely on the port side at Dundee and in support roles.

Looking for stability

Aim for O&M roles. The wind farm is expected to enter full operation in 2027, so service work should follow the installation phase.

Source: Offshore Wind (offshorewind.biz) · Scale figures are rough estimates from field experience, not official numbers.